Current Road Work

Road Work Scheduled for 2018

Shiloh Paving & Excavating will begin paving township roads beginning the week of July 16th. Weather permitting work will take about 3 weeks to complete. The following roads will be paved:

  • Emig Mill Road between Carlisle & Mayfield.
  • Rohlers Church Road between Crone & Circle.
  • Emig School Road 280’ at township line.
  • Blackberry Road 450’ of old road near the 2500 & 2600 block.

Stewart & Tate will begin placing a bituminous seal coat on the following township roads beginning around of July 18th. Weather permitting work will take about 2 week to complete. The following roads will be sealed:

  • Butter Road between Bull & Meadow (Dover Borough)
  • Pinchtown Road between Admire & a point 3600’ towards Dairy
  • Piney Hollow Road between Harmony Grove & Conewago
  • Timberland Road between Harmony Grove & Piney Hollow
  • Bluebird Road between Rohlers Church & a point 800’ south
  • Conewago Road between Carlisle & Fish and Game.
  • Conewago Road between Harmony Grove & Piney Hollow

 

[Best_Wordpress_Gallery id=”12″ gal_title=”Road Work Completed”]

SR 074 Bridge Plans – This project is tentatively scheduled for Summer 2017 and the bridge will not be closed during construction.

 