Project Delays on Rohlers Church Bridge & Poplars Rd Drainage Project

Material issues have delayed the Rohlers Church Road Bridge Replacement and Poplars Road Drainage projects in Dover Township:

  • Rohlers Church Road Bridge #426 – the contractor recently contacted us indicating that the fabricator of the box culvert has had scheduling delays. Construction will now begin in March 2021 and is anticipated to be completed before May 14, 2021.
  •  

  • Poplars Road Drainage Improvements (1900 block) – the contractor had ask for a time extension due to precast concrete delays and changes in pipe materials. Work should be complete before December 14, 2020, and if necessary, final paving will be completed in the Spring of 2021.

Both projects will require the road to be closed to all traffic during construction. Thank you for your patience while traveling our roads during the construction period.