Pinchtown Rd FDR & Paving

Dover Township plans to finish the last section of Pinchtown Road using the “Full Depth Reclamation Process and Paving Overlay” (FDR). The approximate length of this project is forty-one hundred (4,100) linear feet of roadway. This process will consist of reclaiming a depth of twelve (12) inches by twenty (20) feet in width. The roadway will be ground up, re-laid, cement spread over the surface, reground, graded to the proper slope, then compacted.

The road will need to sit for approximately two (2) weeks before the overlay can take place. After the two (2) weeks, the contractor will do an overlay of three (3) inches of compacted twenty-five (25) mm asphalt. The final step of this process, the contractor will do an overlay of one and a half (1.5) inches of compacted nine and a half (9.5) mm asphalt. The Final roadway will be an eighteen (18) foot wide paved roadway with a two (2) foot shoulder on either side of the travel lane. Please us the provided links to see the process.

Pinchtown Rd FDR and Paving Map
Step 1 – Road Widening

 

Step 2 – FDR

 

Step 3 – FDR with Cement Mix